Innovating Works

H2020

Cerrada
HORIZON-SESAR-2022-DES-IR...
HORIZON-SESAR-2022-DES-IR-01-WA6-3: Industrial Research & Validation for Master Plan Phase C Capacity-on-Demand and Dynamic Airspace
ExpectedOutcome:The key objective of this topic is to achieve TRL6 maturity level for solutions under phase C of the ATM Master Plan 2020 relating to capacity on demand and dynamic airspace management.
Sólo fondo perdido 0 €
Europeo
Esta convocatoria está cerrada Esta línea ya está cerrada por lo que no puedes aplicar. Cerró el pasado día 13-10-2022.
Se espera una próxima convocatoria para esta ayuda, aún no está clara la fecha exacta de inicio de convocatoria.
Por suerte, hemos conseguido la lista de proyectos financiados!
Presentación: Consorcio Consorcio: Esta ayuda está diseñada para aplicar a ella en formato consorcio..
Esta ayuda financia Proyectos:

ExpectedOutcome:The key objective of this topic is to achieve TRL6 maturity level for solutions under phase C of the ATM Master Plan 2020 relating to capacity on demand and dynamic airspace management.

Capacity. Capacity is increased through dynamic airspace management, responding with flexibility to airspace users’ flight trajectory needs.Safety. Safety is improved through better anticipation and management of potential overload.Efficiency. Efficiency is increased thanks to monitoring of DCB measures and network performance, and the implementation of corrective actions.Cost-efficiency. Progress in this work area enables improved ATM resource planning and better use of existing capacities, leading to reduced ATC and airport capacity costs.Predictability. The provision of information regarding the planned network situation, taking into account all known constraints and time deviation, will be made possible by anticipating demand–capacity imbalance and improving the implementation of DCB solutions.Flexibility. There will be a higher degree of common awareness among all stakeholders and greater access to opportunities to remedy the situation in the event of late changes i... ver más

ExpectedOutcome:The key objective of this topic is to achieve TRL6 maturity level for solutions under phase C of the ATM Master Plan 2020 relating to capacity on demand and dynamic airspace management.

Capacity. Capacity is increased through dynamic airspace management, responding with flexibility to airspace users’ flight trajectory needs.Safety. Safety is improved through better anticipation and management of potential overload.Efficiency. Efficiency is increased thanks to monitoring of DCB measures and network performance, and the implementation of corrective actions.Cost-efficiency. Progress in this work area enables improved ATM resource planning and better use of existing capacities, leading to reduced ATC and airport capacity costs.Predictability. The provision of information regarding the planned network situation, taking into account all known constraints and time deviation, will be made possible by anticipating demand–capacity imbalance and improving the implementation of DCB solutions.Flexibility. There will be a higher degree of common awareness among all stakeholders and greater access to opportunities to remedy the situation in the event of late changes in capacity or demand.
Scope:To achieve the expected outcomes, all or some of the following should be addressed.

Increased flexibility in ATCO validations within an ATSU or between two ATSUs with similar consoles, tools and HMIs (typically, but not necessarily, from the same ANSP). Standardisation of ATCO procedures and more generic en-route controller procedures can reduce the amount of training required for en-route or TMA controllers to be endorsed and/or to stay current in a sector or group of sectors, thanks to new tools and/or procedures. The objective is to allow more flexible rostering within a centre or across ATSUs from the same ANSP thanks to the virtual centre concept (assuming that the ATSUs use similar consoles and tools). This also includes the development of smart sector grouping options, so that controllers can remain validated for the same number of sectors as today, but the number of different sector groups is increased, in order to increase the flexibility of rostering processes. It also includes innovative concepts for currency requirements based on recording additional data compared with today (e.g. traffic types, traffic levels) so that not all hours on console count the same or the total number of hours required for currency remain the same but requirements on a sector are loosened (e.g. by counting hours in a neighbouring sector with a certain weighting). This concept may help controllers to accept delegation of airspace as outlined in the airspace architecture study and as per the virtual centre solution. The objective is to complete TRL6 (PJ.10-W2-73 IFAV and PJ.33-W2-01).Increased flexibility in ATCO validations through night-only validations within an ATSU or between two ATSUs with similar console tools and HMIs (typically, but not necessarily, from the same ANSP). The validation of a controller to work in a sector at top capacity during the day requires detailed knowledge of airports, coordination procedures, traffic patterns and sector transfer conditions that are never applied during night shifts (because certain airports are closed, some sectors are always band-boxed and some traffic flows do not happen during the night). The objective of this activity is to develop a concept for night-only validation, aiming at reaching TRL6. This could, for example, be applied within a centre with multiple sector groups: a controller could be validated for day operations only for one sector group but could work nights in all sector groups, thus increasing flexibility in rostering. Another use case would be having a group of controllers specialising in night shifts only, and able to work in both their own ATSU and a second ATSU, thus allowing the two ATSUs to be consolidated during the night (PJ.10-W2-73 IFAV and PJ.33-W2-01).Collaborative management at regional airports. The airport operations centre concept was originally designed for large airports during previous SESAR phases and further developed through the total airport management project, based on a platform/operational structure that collaboratively and proactively manages airport operations performance. Although regional airports do not generally experience operational constraints at the same scale as larger airports, they do experience issues that result in their operations underperforming. A lack of communication and information shared among stakeholders can cause unforeseen deterioration in airport performance, with potential knock-on effects on the ATM network. This covers the development of a ‘Lite’ APOC, aimed at improving inbound, turnaround and outbound predictability based on an enhanced local collaborative environment and better connectivity with the ATM network. Airport and network information will thus be exchanged more reliably, resulting in improved situational awareness and supporting pre-tactical and tactical decision-making. The objective is to complete TRL6 (PJ.04-W2-28.2).Environmental performance management. Management of airport operations often necessitates trade-offs between different performance criteria (flight delay, passenger satisfaction, resource availability, etc.). The objective is to reach TRL6 for solutions focused on environmental performance management, with the aim of integrating environmental considerations into the overall airport operations management process, bringing the issue of environmental performance into the decision-making process (PJ.04-W2-29.3).
ver menos

Temáticas Obligatorias del proyecto: Temática principal:

Características del consorcio

Ámbito Europeo : La ayuda es de ámbito europeo, puede aplicar a esta linea cualquier empresa que forme parte de la Comunidad Europea.
Tipo y tamaño de organizaciones: El diseño de consorcio necesario para la tramitación de esta ayuda necesita de:

Características del Proyecto

Requisitos de diseño: Duración:
Requisitos técnicos: ExpectedOutcome:The key objective of this topic is to achieve TRL6 maturity level for solutions under phase C of the ATM Master Plan 2020 relating to capacity on demand and dynamic airspace management. ExpectedOutcome:The key objective of this topic is to achieve TRL6 maturity level for solutions under phase C of the ATM Master Plan 2020 relating to capacity on demand and dynamic airspace management.
¿Quieres ejemplos? Puedes consultar aquí los últimos proyectos conocidos financiados por esta línea, sus tecnologías, sus presupuestos y sus compañías.
Capítulos financiables: Los capítulos de gastos financiables para esta línea son:
Personnel costs.
Subcontracting costs.
Purchase costs.
Other cost categories.
Indirect costs.
Madurez tecnológica: La tramitación de esta ayuda requiere de un nivel tecnológico mínimo en el proyecto de TRL 4:. Es el primer paso para determinar si los componentes individuales funcionarán juntos como un sistema en un entorno de laboratorio. Es un sistema de baja fidelidad para demostrar la funcionalidad básica y se definen las predicciones de rendimiento asociadas en relación con el entorno operativo final. + info.
TRL esperado:

Características de la financiación

Intensidad de la ayuda: Sólo fondo perdido + info
Fondo perdido:
0% 25% 50% 75% 100%
Para el presupuesto subvencionable la intensidad de la ayuda en formato fondo perdido podrá alcanzar como minimo un 100%.
The funding rate for RIA projects is 100 % of the eligible costs for all types of organizations. The funding rate for RIA projects is 100 % of the eligible costs for all types of organizations.
Garantías:
No exige Garantías
No existen condiciones financieras para el beneficiario.

Información adicional de la convocatoria

Efecto incentivador: Esta ayuda no tiene efecto incentivador. + info.
Respuesta Organismo: Se calcula que aproximadamente, la respuesta del organismo una vez tramitada la ayuda es de:
Meses de respuesta:
Muy Competitiva:
No Competitiva Competitiva Muy Competitiva
No conocemos el presupuesto total de la línea
Minimis: Esta línea de financiación NO considera una “ayuda de minimis”. Puedes consultar la normativa aquí.

Otras ventajas

Sello PYME: Tramitar esta ayuda con éxito permite conseguir el sello de calidad de “sello pyme innovadora”. Que permite ciertas ventajas fiscales.